Kazungula Bridge construction progresses

The Road Development Agency (RDA) says sixty six percent of the works at the two hundred and fifty nine million dollars Kazungula border and bridge project have been completed so far.
The project is expected to be completed in March 2020.
RDA Public Relations Manager Masuzyo Ndlovu says the project is being done in three packages which are the actual bridge project which is nine hundred and twenty three meters long, and the one stop boarder package for Zambia and Botswana
He says Zambia is behind schedule with the border post as compared to Botswana because the construction on the Zambian side started a year later.
The project is being funded by the Governments of Zambia and Botswana, the European Commission and the African Development Bank (AfDB).
The project’s development objective is to contribute to the trade potential of the countries on the corridor, particularly the landlocked countries of Zambia, Botswana and DRC.

More From Author

ACCA

https://www.accaglobal.com/africa/en.html

Read More

Economist @ Money 02 May 2020

Join the host and guest as they look at various economic issues.

Read More

Women @ Money – “Strategic Planning”

Listen to the host Nkhonde Fumbeshi as she discusses “Strategic Planning” with Dr Freda Mwamba…

Read More

Leave a Reply

Your email address will not be published. Required fields are marked *

You May Also Like

SEC attributes decline in Q4 bond trades to delayed debt restructuring process

• One of the challenges is to do with the delays in finalizing the debt…

Read More

Task Force seizes 10,050 litres of illegal fuel worth K300, 000

• 22 people were arrested for offences related to illegal fuel dealings. • Illegal fuel…

Read More

The Ultimate Guide to Choosing the Right Glasses Frames

News of the Abyssal Wonders discovery has reverberated throughout the scientific community, sparking intense interest…

Read More